JURISDICTION      : SUPREME COURT OF WESTERN AUSTRALIA

                                      IN CHAMBERS

CITATION               : MILLER -v- MONAGHAN [2026] WASC 441

CORAM                   : LUNDBERG J

HEARD                    : 9 OCTOBER 2026

DELIVERED           : 12 OCTOBER 2026

FILE NO/S               : ARB 6 of 2026

BETWEEN               : JONATHAN NEIL MILLER T/AS FORTRESS CONSTRUCTION WA

                                      Plaintiff

                                      AND

                                      ALISE LILLY MONAGHAN

                                      Defendant

Catchwords:

Arbitration – Application for order to appoint an arbitrator pursuant to s 11 of the Commercial Arbitration Act 2012 (WA) – Whether the requirements of the legislation satisfied by the plaintiff – Refusal by appointing authority to appoint arbitrator – Turns on own facts

Costs – Whether successful plaintiff entitled to costs of the application – Turns on own facts

Legislation:

Building Services (Complaint Resolution and Administration) Regulations 2011 (WA)

Building Services (Complaint Resolution and Administration) Act 2011 (WA)

Commercial Arbitration Act 2012 (WA), s 7, s 11

Home Building Contracts Regulations 1992 (WA), reg 2A

Home Building Contracts Act 1991 (WA), s 3, s 14, s 27

Result:

Application granted and costs orders made in favour of the plaintiff.

Category: B

Representation:

Counsel:

Plaintiff:S Mintz
Defendant:In Person

Solicitors:

Plaintiff:Vogt Legal
Defendant:In Person

Case(s) referred to in decision(s):

<CRJ>

Browne’s Limestone Constructions Pty Ltd v Georgiou Group Pty Ltd [2021] WASC 181

EEPL Holdings v Clifford Chance [2026] WASC 368

Fitzpatrick v Emerald Grain Pty Ltd [2017] WASC 206

Frigger v Lean [2012] WASCA 66

Gemcan Constructions Pty Ltd v Westbourne Grammer School [2020] VSC 429

Henderson & Anor v Aintree Holdings Pty Ltd [2021] WASAT 113

IBM Australia Ltd v National Distribution Services Ltd (1991) 22 NSWLR 466

Latoudis v Casey (1990) 170 CLR 534

Maritime Services Board (NSW) v Liquor Administration Board (1990) 21 NSWLR 180

Pipeline Services WA Pty Ltd v ATCO Gas Australia Pty Ltd [2014] WASC 10

Shakur v Aintree Holdings Pty Ltd [2015] WASAT 12

Smolarek v Roper [2009] WASCA 124 (S)

Tulip Bay Pty Ltd v Structural Monitoring Systems Ltd [2019] WASC 223

</CRJ>

Table of Contents

Overview

Factual background

The Building Contract

The additional works undertaken by the plaintiff

The Notice of Dispute

Request for appointment by the HIA

The plaintiff makes a further attempt to have an arbitrator appointed by consent

Consent from Mr Ellis to be appointed

Proposed complaint to the Building Commissioner

The legislative framework

Issues arising on this application

Disposition

Whether there is a valid arbitration agreement

Whether the dispute falls within the arbitration agreement

Whether the requirements of s 11(4) have been satisfied

Whether the identified arbitrator is appropriate

Costs

Conclusion and orders

LUNDBERG J:

Overview

  1.         The court has before it an application for the court to appoint Mr Scott Ellis as the arbitrator for the purposes of a proposed arbitration which has been initiated by the plaintiff.  The application was brought by the plaintiff by originating summons filed on 18 September 2026, supported by a comprehensive affidavit affirmed by the plaintiff on 15 September 2026 (Miller Affidavit).
  2.         The order is sought under s 11(4) of the Commercial Arbitration Act 2012 (WA) (CAA), as a result of the parties’ failure to agree on an arbitrator and the subsequent refusal of the appointing authority identified in the parties’ arbitration agreement to appoint an arbitrator.  
  3.         Section 11(4) provides as follows:

(4)       Where, under an appointment procedure agreed on by the parties —  

(a)          a party fails to act as required under the procedure; or

(b)          the parties, or 2 or more arbitrators, are unable to reach an agreement expected of them under the procedure; or

(c)          a third party, including an institution, fails to perform any function entrusted to it under the procedure,

any party may request the Court to take the necessary measure, unless the agreement on the appointment procedure provides other means for securing the appointment.

  1.         The arbitration agreement is found in cl 18 of the building contract executed by the parties, being a contract for the construction of a residential dwelling on the defendant’s land (Building Contract).[1]  The plaintiff is a builder of residential homes and the defendant is the registered proprietor of land in Madora Bay, Western Australia.  The clause provides as follows:[2]

18.       Disputes 

(a)       In any dispute, disagreement or difference between the Owner and the Builder [sic – arises] at any time relating to this Contract then subject to the right of either party to apply to the Building Commissioner or State Administrative Tribunal, or any other relevant Statutory Authority, either party shall give to the other notice of such dispute, disagreement or difference and at the expiration of TEN (10) Working days thereafter and in the absence of any settlement the same shall be referred to:

(i)           a single mediator appointed by mutual consent; or

(ii)          a single arbitrator appointed by mutual consent; or

(iii)         in the event that neither (i) or (ii) are satisfied within FIVE (5) Working days or mediation is not successful, a single arbitrator shall be appointed by the president or the President’s nominee of the Housing Industry Association (Western Australian Region), provided that such arbitrator shall be a graded Arbitrator approved by the Institute of Arbitrators Western Australian Chapter.

(b)       The conduct of the Arbitrator shall be in accordance with and subject to the provisions of the Commercial Arbitration Act 1985 and the decision of the single arbitrator appointed shall be final.  The rights and obligations of the parties under this Contract shall be modified only to the extent made necessary by such arbitration.

(c)       This Contract and the parties’ rights and obligations under this Contract shall in all respects be governed by of the laws of the State of Western Australia and the parties hereto irrevocably submit themselves to the exclusive jurisdiction of the Courts of Western Australia.

  1.         The plaintiff’s application was first heard on 5 October 2026, and adjourned to allow the defendant an opportunity to formally engage solicitors.  The defendant was unable to secure legal representation on the record, however, and the application then proceeded substantively on 9 October.
  2.         At the conclusion of the hearing, I indicated I was satisfied the order should be made and, having heard from the parties on the issue of costs, I indicated I was satisfied that an order should be made in the plaintiff’s favour in that regard.  These are my reasons for making those orders.

Factual background

The Building Contract

  1.         The Building Contract was entered into by the parties in April 2024.  There is no doubt as to the existence of that contract, which was produced in evidence before me.  It appears to be a relatively standard form building contract.  The contract sum is stated as $675,910, including GST.  
  2.         The Building Contract includes a comprehensive variation clause, in cl 12, which provides:

12.       Variations

(a)        If the Owner wishes to make any variation to the Works and/or the Contract Documents the Owner or the Owner’s agent shall give the Builder a written request for such variation.  The Builder may decline to agree to the variation requested but in the event that the Builder is prepared to agree to the variation:

(i)           the Builder shall prepare and give to the Owner or the Owner’s agent a variation document setting out the terms of, and the cost to be incurred on account of, the variation;

(ii)          the Owner or the Owner’s agent shall sign and return the variation document to the Builder;

(iii) the Builder or the Builder’s agent shall sign and insert in the variation document the date that the Builder signs it and forward a signed copy to the Owner or the Owner’s agent as soon as is reasonably practicable thereafter and before the work to which the variation relates is commenced; and

(iv)         the variation shall be carried out as if it were part of the Works under the Contract.

(b)       The Builder shall be entitled to vary all or any of the Works and/or the Contract Documents made necessary by:

(i)           any written direction lawfully given by a building surveyor or other person acting under a written law; or

(ii)          circumstances that could not reasonably have been foreseen by the Builder at the time when this Contract was entered into if the Builder gives to the Owner, within the time specified in Clause 12(c), a statement setting out the reason for, and the cost to be incurred on account of, the variation and a copy of any direction referred to in Clause 12(b)(i).

PROVIDED THAT Clause 12(b)(ii) shall not enable the Builder to make any variation by reason only of an increase in the costs of labour (including related overhead expenses) or materials or both, to be incurred by the Builder.

PROVIDED ALSO THAT where an Owner is given a statement by the Builder for the purposes of Clause 12(b)(ii) and the Owner considers that the variation is not one to which Clause 12(b)(ii) applies then the Owner may make an application to the Building Commissioner or State Administrative Tribunal for relief under Section 17 of the Home Building Contracts Act 1991 within TEN (10) Working days of being given the statement.

(c)        The Builder shall give the statement referred to in Clause 12(b) to the Owner within TEN (10) Working days after the Builder:

(i)           received notice of the direction under Clause 12(b)(i); or

(ii)          became aware or should reasonably have become aware of the circumstances referred to in Clause 12(b)(ii), as the case may be.

(d)       If any variation to the Works and/or the Contract Documents is required pursuant to Clause 3(d), 4(c), 5(a) – (h) or 21 but not as a result of a direction under Clause 12(b)(i) or the circumstances referred to in Clause 12(b)(ii) then the Builder shall prepare and give to the Owner a variation document setting out the terms of and the cost to be incurred on account of the variation so required and:

(i)          if the Owner signs and returns the variation document to the Builder then the provisions of Clause 12(a)(iii) and (iv) shall also apply to the variation; or

(ii)         if the Owner does not sign and return the variation document to the Builder within FIVE (5) Working days of being given the variation document then the Builder shall be entitled to either carry out the work required but without any adjustment to the Contract Price or to terminate this Contract pursuant to Clause 16(g);

(e)        The price of a ‘variation’ shall, unless previously agreed in writing:

(i)           if the amount is additional to the Contract Price, be the reasonable price for the variation including an amount for the Builder’s margin being that percentage of such costs as set forth in Item 11 of the Schedule and it shall be added to the Contract Price, and unless previously paid, shall be added to the next progress payment due after the execution of such work; or

(ii)         it shalt result in a decrease to the Contract Price, be the reasonable price for the variation and it shall not include any amount for the Builder’s margin and such decrease shall be deducted from the final payment hereunder.

(f)        The Owner shall obtain the consent of the Owner’s lender (if any) prior to requesting or authorising the Builder to carry out extra work or to vary the Works in any way.

(g)       The Builder may, at any time prior to the commencement of any building work that is to be performed by way of a variation pursuant to the provisions of this Contract, by notice in writing require the Owner to satisfy the Builder that the Owner is able to pay the cost to be incurred on account of the variation by production of evidence in writing and if the Owner shall fail to do so within TEN (10) Working days of the receipt of such notice the Builder may terminate this Contract immediately by notice in writing given to the Owner within a further TEN (10) Working days.

The additional works undertaken by the plaintiff

  1.         On 9 March 2026, the plaintiff rendered an invoice to the defendant in respect of the work undertaken between August 2025 and December 2025, said to represent variations to the works under the Building Contract.  The works were carried out by the plaintiff on a ‘cost-plus’ basis.  The parties are in dispute regarding this invoice, which is in the amount of $106,773.52.[3]  The parties are also in dispute as to the cost of securing the power supply to the residence.[4]  
  2.         The plaintiff builder accepts that the variation procedure in cl 12 was not followed in respect of every item of additional work, although initially some variation orders were prepared, and then signed by the defendant and her husband.[5]  The plaintiff deposes in his affidavit that the additional works were undertaken in an expedited fashion at the request of the defendant’s husband, being works not falling within the scope of the ‘Works’ under the Building Contract.  The plaintiff deposes that he and the defendant’s husband agreed to the works being carried out on a cost-plus basis:[6]

[45]    In that context, to keep the Works progressing and to allow Mr and Mrs Monaghan to have their variations, I said to Mr Monaghan, at a meeting at 10 Sabina Drive in late-September 2025, “All these changes are getting too complicated to keep up with the paperwork with, so all these additional works will need to be carried out at cost plus a reasonable margin and reconciled as we go, if we ‘re to get you in before Christmas”. Mr Monaghan said to me: “That’s fine “.

  1.          I should emphasise that the parties are not in agreement as to the facts which have given rise to the disputes.  There are several disputed conversations.  Within the Miller Affidavit, the plaintiff has deposed to his recollection of the events, including discussions with the defendant and her husband.  The defendant filed an affidavit on 8 October 2026 (Monaghan Affidavit) which also provides some background to the dispute from her perspective, as well as her concerns regarding the accuracy of the invoices issued to her and her attempts to resolve the dispute.

The Notice of Dispute

  1.         The dispute between the parties led to the plaintiff issuing a notice of dispute, dated 19 May 2026, seeking to refer the dispute to arbitration under cl 18(a) of the Building Contract (Notice of Dispute).[7]  The Notice of Dispute is comprehensive.  The opening paragraphs make plain the intention of the plaintiff, recognising there is an obvious error in the second paragraph:

1.         This is a Notice of Dispute issued by the Builder to the Owner, giving notice of a dispute, disagreement or difference which has arisen in relation to the Contract, under cl. 18(a).

2.         Unless the dispute, as articulated below, is resolved within five (5) working days of the date of this notice, the Owners [sic- the Builder] intend to refer this matter to an arbitration under cl. 18(a) of the Contract and the Commercial Arbitration Act 2012 (WA).

  1.         The Notice of Dispute incorporates a schedule of payment claims and a schedule of the variations claimed by the plaintiff.  By [31] of the Notice of Dispute, the defendant was requested to pay the outstanding sums.  The Notice of Dispute then states that:

REFERRAL TO ARBITRATION

[32]     Should the dispute not be resolved by the Owner taking the steps referred to in par. 31 above within FIVE (5) working days of the date of service of this Notice, the Builder will seek a referral of this matter to an arbitration.

[33]     In the event that the dispute as articulated above is unable to be resolved in the above timeframe, the Builder proposes that the Parties agree to appoint one of the following persons as arbitrator…

  1.         The Notice of Dispute then identifies three barristers at the Western Australia bar, one of whom was Mr Ellis.
  2.         The Notice of Dispute continues:

[34]     The Owner is invited to provide names of any other persons that the Owner would like the Builder to consider for the nomination as arbitrator in respect of the above dispute.

[35]     If the Owner and the Builder are unable to reach agreement as to the nomination as arbitrator, the Builder will provide this notice to the President of the Housing Industry Association, requesting that the President or his/her nominee appoint an arbitrator.

  1.         The defendant did not consent to the appointment of an arbitrator and did not identify an alternative person to be so appointed. 

Request for appointment by the HIA

  1.         On 28 May 2026, the plaintiff’s solicitors wrote to the President of the Housing Industry Association (HIA), as the named appointing authority under the Building Contract, to request the appointment of an arbitrator to the dispute.[8]
  2.         The HIA declined to make an appointment, as appears from the letter sent by the HIA in response on 17 June 2026.[9]  The explanation for the refusal was that the Building Contract had not been registered with the HIA, which involves a process of paying a fee and also seeking permission to modify or adapt the terms of the standard HIA contract.   Accordingly, the HIA indicated it did not accept it had any role under the clause of this particular contract.   On its face, that is an understandable response.

The plaintiff makes a further attempt to have an arbitrator appointed by consent

  1.         In light of this, on 11 July 2026, the plaintiff’s solicitors wrote to the defendant proposing that the defendant consent to one of the arbitrators proposed by the plaintiff, or to nominate another person.[10]   Importantly, the letter from the plaintiff’s solicitors foreshadowed:

(a)       an application to this court under s 11(4) of the CAA without further notice; and

(b)       an application being made to the court for a costs order in the event the application under s 11(4) was successful.

  1.         The plaintiff’s solicitors encouraged the defendant, within the letter, to seek legal advice in relation to the matters in the letter and in the Notice of Dispute.  The letter sought a response by 22 July 2026.
  2.         The defendant responded on 17 July 2026.[11]  The defendant refused to consent to any of the arbitrators proposed by the plaintiff and refused to participate in the arbitration process.  The defendant made it clear in her response that the works in question were outside the scope of the Building Contract, and she referred to the conduct of the plaintiff as an ‘unreasonable escalation’.  The defendant identified several points of complaint regarding the conduct of the builder, the absence of signed variations, the incorrect application of a cost-plus approach by the builder, and errors in the invoicing, among other matters.

Consent from Mr Ellis to be appointed

  1.         In the meantime, the plaintiff’s solicitors approached Mr Ellis seeking his consent to be appointed, to which Mr Ellis promptly responded indicating he was able to accept the appointment and was not aware of any matters which might give rise to justifiable doubts as to his impartiality or independence.[12]

Proposed complaint to the Building Commissioner

  1.         In parallel to the above matters, the defendant issued to the plaintiff a notice of proposed complaint to the Building Commissioner, on about 10 July 2026.[13]  
  2.         The notice was issued in apparent compliance with the Building Services (Complaint Resolution and Administration) Regulations 2011 (WA) (Building Services Regulations), which require that a party provide the proposed respondent with 14 days’ notice before making a complaint to the Building Commissioner.[14]  The complaint itself may then be made under s 5 of the Building Services Complaint Resolution and Administration) Act 2011 (WA) (Building Services Act).   Section 5 provides:

5.         Making complaint about building service or home building work contract matter

(1)       Subject to the regulations, a person may make a complaint to the Building Commissioner about a regulated building service not being carried out in a proper and proficient manner or being faulty or unsatisfactory.

(2)       An owner or builder under a home building work contract may make a complaint to the Building Commissioner about a matter referred to in the Home Building Contracts Act 1991 section 17 or 20 or Schedule 1 clause 5.

  1.         The plaintiff’s solicitors responded to this notice in a letter sent on 16 July 2026, asserting that the Building Commissioner did not have jurisdiction to hear a contractual complaint under the Building Contract between the parties, and that the relief which was sought (being in the nature of personal injuries) was beyond the jurisdiction of the Building Commissioner or the State Administrative Tribunal.[15]
  2.         In particular, the plaintiff’s solicitors noted the contract sum under the Building Contract exceeded $500,000, being the sum specified in reg 2A of the Home Building Contracts Regulations 1992 (WA) which limits the definition of ‘home building work contract’ in s 3 of the Home Building Contracts Act 1991 (WA).
  3.         The plaintiff’s solicitors also drew attention to s 8 of the CAA, which provides that a ‘court before which an action is brought in a matter which is the subject of an arbitration agreement must, if a party so requests not later than when submitting the party’s first statement on the substance of the dispute, refer the parties to arbitration unless it finds that the agreement is null and void, inoperative or incapable of being performed’.  The solicitors then made a reference to decisions of the State Administrative Tribunal to the effect that s 8 applies to proceedings referred to the Tribunal under the Building Services Act, namely Henderson & Anor v Aintree Holdings Pty Ltd[16] and Shakur v Aintree Holdings Pty Ltd.[17]
  4.         The defendant ultimately withdrew her complaint to the Building Commissioner on 6 October 2026.[18]

The legislative framework

  1.         Section 7 of the CAA describes what an arbitration agreement is and the necessary form requirements.  
  2.         Section 11(2) of the CAA provides that the parties to an arbitration agreement are free to agree on a procedure of appointing the arbitrator or arbitrators for their dispute, subject to compliance with s 11(4) and s 11(5).  Where the parties have not agreed on a procedure for the appointment of an arbitrator or arbitrators, s 11(3) applies.  As there was an agreed procedure in the Building Contract in the present case, s 11(3) is not applicable.
  3.         Sub-sections 11(4), 11(5) and s 11(6) of the CAA provide as follows:

(4)          Where, under an appointment procedure agreed on by the parties —  

(a)          a party fails to act as required under the procedure; or

(b)          the parties, or 2 or more arbitrators, are unable to reach an agreement expected of them under the procedure; or

(c)          a third party, including an institution, fails to perform any function entrusted to it under the procedure,

any party may request the Court to take the necessary measure, unless the agreement on the appointment procedure provides other means for securing the appointment.

(5)          A decision within the limits of the Court’s authority on a matter entrusted by subsection (3) or (4) to the Court is final.

(6)          The Court, in appointing an arbitrator, is to have due regard to any qualifications required of the arbitrator by the agreement of the parties and to such considerations as are likely to secure the appointment of an independent and impartial arbitrator.

  1.         An authoritative commentary on the legislation, Australian Commercial Arbitration (3rd edition, 2026), provides a useful explanation of s 11(4), in the following terms:[19]

Where there has been an agreed procedure for appointment of an arbitrator or arbitrators and a failure of a party or an arbitral institution to make an appointment, this subsection applies.

Section 11(4)(a) and (6) were applied by Kenneth Martin J in Tulip Bay Pty Ltd v Structural Monitoring Systems Ltd [2019] WASC 223 to appoint a second arbitrator.  The appointment of a second arbitrator to a panel of three arbitrators was impeded by the incorrect wording in the parties Technology Agreement made in 1999 that referred to a non-existent appointing authority leading to a “dysfunctionality” in regard to the opposed appointment of the second arbitrator.

The discretionary considerations of urgency and expertise of the person to be appointed arbitrator in the context of the arbitrator already appointed and issues to be decided at the arbitration were applied.

Issues arising on this application

  1.         In the present case, having regard to the terms of s 11 of the CAA, the plaintiff’s application required the court to be satisfied of the following matters.
  2.         First, that a valid arbitration agreement within the meaning of s 7 of the CAA is in existence.
  3.         Second, that the identified dispute falls within the parameters of the arbitration agreement.
  4.         Third, that one of the bases for the exercise of the court’s power in s 11(4) has been demonstrated.  In the present case, the plaintiff principally relied on s 11(4)(c), being the failure by a third party, including an institution, to perform any function entrusted to it under the parties’ agreed procedure.  The plaintiff alternatively relied on s 11(4)(a) and s 11(4)(b).
  5.         Fourth, that the identified arbitrator is an appropriate person to be appointed to resolve the dispute in question, which requires the court to have due regard to the matters stated in s 11(6).

Disposition

 Whether there is a valid arbitration agreement

  1.         There can be no doubt that cl 18 of the Building Contract is an arbitration agreement within the meaning of s 7 of the CAA.  The terms of cl 18 reveal the objective intention of the parties that arbitration is the means by which their disputes are to be resolved.[20]  
  2.         Further, the failure by the named appointing authority to appoint an arbitrator as part of the agreed procedure does not operate to invalidate the arbitration agreement.  The machinery for the appointment of an arbitrator is not an essential characteristic of an enforceable arbitration agreement and, in any event, the terms of the CAA provide the required statutory mechanism for the resolution, review and enforcement of domestic arbitration agreements.[21]  As earlier noted, this court has engaged the provisions of s 11(4) of the legislation in circumstances in which the contract under consideration referred to an appointing authority which did not exist and which appeared never to exist.[22]

Whether the dispute falls within the arbitration agreement

  1.         This issue requires the arbitration agreement to be construed, in accordance with the principles which apply to the construction of all commercial contracts.   I recently set out the applicable principles in EEPL Holdings v Clifford Chance,[23] which I will apply to the present issue.  The text of the clause in question should be read with a broad, flexible, liberal and flexible approach so as to promote the resolution of disputes in a single forum, provided that is consistent with the language used in the instrument.[24]  
  2.         The terms of the arbitration agreement in the Building Contract in the present case are broadly stated, referring to any ‘dispute, disagreement or difference between the Owner and the Builder’ and employing the term ‘relating to’ so as to signify the connection between the dispute and the Building Contract.
  3.         The phrase ‘relating to’ has been described as a term of the widest import.   Martin CJ in Fitzpatrick v Emerald Grain Pty Ltd referred to the phrase as follows:[25]

Clause 32 of each version of the Conditions also uses the expression ‘relating to’ to describe the requisite degree of connection between a dispute or claim coming within the arbitration agreement and the substantive agreement.  The cases dealing with the use of that expression in an arbitration agreement establish that it is properly construed as a term of the widest import which should not, in the absence of compelling reasons, be read down. (citated omitted)

  1.         In reaching this view, Martin CJ relied on the decision of the NSW Court of Appeal in IBM Australia Ltd v National Distribution Services Ltd.[26]  In that case, each member of the Court of Appeal emphasised the breadth of the above phrase.  Clarke JA held as follows:[27]

But meaning must be given to the phrase “related to this agreement or any breach thereof”: Ashville Investments Ltd v Elmer Contractors Ltd [1989] QB 488 at 503, per Balcombe LJ.   It is not only claims arising out of the agreement or any breaches of it which are covered but also those related to the agreement and any breaches of it.

The phrases “in relation to” or “related to” are of the widest import and should not, in the absence of compelling reasons to the contrary, be read down: Fountain v Alexander (1982) 150 CLR 615 at 629; Dowell Australia Ltd v Triden Contractors Pty Ltd [1982] 1 NSWLR 508 at 511 and Ashville Investments Ltd v Elmer Contractors Ltd.   In its context I would, in the absence of contrary indications in the contract, understand the clause to be sufficiently wide to encompass claims that pre-contractual misrepresentations induced the complaining party to enter the contract.

There are no indications in the contract that the words should be construed narrowly.  Nor, in my opinion, are there any compelling reasons in favour of reading down the meaning of the phrase.  On the contrary there are powerful considerations in favour of the contrary view.  The consequence of an interpretation of the arbitration clause which excludes the claims under the Act would be that the causes of action based upon breaches of the contract would remain with the arbitrator, and be decided by him, and those in which reliance were placed upon ss 52, 82 and 87 of the Act would be determined in a court of law.  As I earlier pointed out this conclusion would follow even in a case in which the same representations were said to ground claims in breach of contract and under the Act.

The parties could hardly be thought to have contemplated that the arbitration clause would work in that way.   It is far more likely that they intended that all disputes between them concerning the terms of the contract, the performance of it and matters connected, in a real sense, with the contract should be referred to the one tribunal for determination.  For my part I would find it difficult to ascribe to the parties to a contract an intention to submit only part of a dispute to an arbitral tribunal reserving the remainder for consideration by the Court as this would, on any view, be inefficient and costly.

  1.         As the plaintiff correctly submitted, and as earlier noted, the scope of an arbitration clause is effectively one of contractual construction, and the text of the clause in question should be read with a broad, flexible, liberal and flexible approach to the construction of the language which promotes the resolution of disputes in a single forum.  There is considerable authority in support of this proposition.[28]  
  2.         As to the present dispute, in his submissions, the plaintiff notes that the Notice of Dispute refers to a dispute concerning the liability to pay Invoice No. 2361 and to reimburse the plaintiff in respect of the costs incurred to supply power to the residence whilst the works were carried out.  The plaintiff contends that the variations in question ‘were requested and carried out on a ‘cost plus’ basis and as such, [the plaintiff] is entitled to be paid the sum which is claimed’.[29]   The submissions continue:[30]

[26] The questions of whether the Variations were carried out, the value of the Variations and Mr Miller’s entitlement are all matters falling for determination within the scope of the foreshadowed arbitration proceedings. It would not be appropriate to determine such matters in the context of the current hearing.

[27] There is an argument potentially available as to whether the Variations-dispute falls within the ambit of the arbitration agreement because the Parties do not appear to have complied with the procedure for the raising of variations under cl. 12 of the Contract.  Whilst it is accepted that neither party complied, that does not preclude the dispute from being arbitral.

  1.         I respectfully agree, bearing in mind the breadth of the arbitration agreement in this case, as objectively assessed.  
  2.         That is, the court can be presently satisfied that, subject to the findings which might be made on the evidence, the subject matter of the variations claimed by the plaintiff is a dispute relating to the Building Contract and capable of being referred to arbitration.  It is at least arguable that, although there was non-compliance with the variation procedure in cl 12 of the Building Contract, the plaintiff may be able to rely on the conduct of the parties to make good his contentions, relaying on some species of estoppel.  Whether that will be the case requires a trier of fact to assess the competing evidence and credibility of the witnesses, which is beyond the scope of this application.  It is enough to say that the plaintiff’s claims for payment of the works undertaken as variations, which form the basis of the dispute between the parties, are matters relating to the Building Contract.
  3.   As to the dispute concerning the supply of electricity, this concerns an allegation of breach of the warranty in cl 3(a)(vi) of the Building Contract on the part of the defendant.  I agree this aspect of the dispute also falls within the scope of the arbitration agreement.
  4.         Finally, I note the arbitration agreement in this case is stated to be subject to ‘the right of either party apply to the Building Commissioner or State Administrative Tribunal, or any other relevant Statutory Authority’.  This exclusion was the subject of submissions by the plaintiff.  As the defendant has withdrawn her complaint to the Building Commissioner, I need not express any view as to the operation of this aspect of cl 18(a).

Whether the requirements of s 11(4) have been satisfied

  1.         I have earlier set out the factual background to the refusal of the identified appointing authority (being the HIA) to appoint an arbitrator.  The terms of s 11(4) will be engaged where a third party fails to perform any function entrusted to that party under an agreed procedure.  
  2.         That is precisely what occurred in the present case.  
  3.         The basis upon which the HIA refused to make a nomination is irrelevant.  The reality is the parties identified the President of that body as an appointing authority and the President has refused to make an appointment.  Further enquiry is unnecessary.
  4.         The present case does not approach the realm of the dysfunctionality which arose in Tulip Bay Pty Ltd v Structural Monitoring Systems Ltd where Kenneth Martin J was confronted with an arbitration agreement which referred to a non-existent appointing authority.  That ‘dysfunctional stalemate situation’ was capable of being resolved by invoking the court’s power in s 11(4).[31]  
  5.         The current case presents as a relatively anodyne circumstance in which a party may resort to s 11(4) to ensure an agreed arbitration procedure is not stultified by an appointing authority’s refusal.

Whether the identified arbitrator is appropriate

  1.         Pursuant to s 11(6) of the CAA, the court, in appointing an arbitrator, is to have due regard to any qualifications required of the arbitrator by the agreement of the parties and to such considerations as are likely to secure the appointment of an independent and impartial arbitrator.  
  2.         The plaintiff submits that the court’s choice of arbitrator will depend on the nature of the dispute and the issues involved and, generally speaking, so much may be accepted.  A fulsome examination of the manner in which s 11(6) is to be applied can be found in the decision of Lyons J in Gemcan Constructions Pty Ltd v Westbourne Grammer School.[32]  However, it is not necessary to dwell too much on the issue in this case, for the following reasons.
  3.         I have been urged by the plaintiff to appoint Mr Ellis as the arbitrator in this case, and no alternative has been proposed.  Mr Ellis has consented to the appointment, and is not aware of any disentitling circumstances which would preclude his appointment.  Mr Ellis is an experienced barrister and a chartered arbitrator.  Moreover, the present dispute strikes me as one requiring a legally trained arbitrator to be appointed, as distinct from, say, a builder or an engineer.  This dispute will give rise to several legal issues (including matters of estoppel and an issue as to the validity of a ‘cost plus’ contract arising under s 14 and s 27 of the Home Building Contracts Act 1991 (WA)), as well as the need to resolve questions of disputed fact, and may also require the expert evidence of competing experts to be evaluated (although I would not place much weight on this final aspect as there is no firm indication as yet that expert evidence will be required).
  4.         In these circumstances, I consider that the appointment of an experienced barrister is appropriate in the circumstances and that the plaintiff’s nominee is appropriate.
  5.         There is one final point to note.  The Building Contract includes in cl 18(a)(iii) a proviso that the ‘arbitrator shall be a graded Arbitrator approved by the Institute of Arbitrators Western Australian Chapter’.  There was no direct evidence before me that Mr Ellis is a ‘graded arbitrator’ in this sense, noting also that the Institute of Arbitrators is no longer known by that name.   
  6.         While I would surmise that Mr Ellis is in fact a graded arbitrator, given his experience, I do not consider the issue is determinative in this case.  I say that because, although the provision in cl 18(a)(iii) is applicable to the appointing power under the contract, s 11(6) requires only that the court have ‘due regard’ to the qualifications required by the parties’ agreement.  The phrase ‘due regard’ in this statutory context means regard which is adequate in all the circumstances,[33] and does not impose a limitation that the court cannot appoint a person unless the qualifications identified in the arbitration agreement are satisfied.
  7.         On my assessment, given the other qualifications of Mr Ellis, the exercise of the power of the court under s 11(4) to appoint him is appropriate in the present circumstances.

Costs

  1.         At the conclusion of the hearing, I heard from the parties as to whether a costs order should be made in favour of the plaintiff, given his success on the application.  I formed the view that such an order should be made.  These are my reasons for doing so.
  2.         The court has a wide discretion to award costs under s 37 of the Supreme Court 1935 (WA).  The discretion regarding costs has been described as ‘absolute, unconfined or unfettered, although a discretion that must be exercised judicially, not arbitrarily or capriciously, or on grounds unconnected with the litigation’.[34]
  3.         An order for the payment of costs by one party is compensatory in nature, not for the purpose of punishment.  Costs are compensatory in the sense that they are awarded to indemnify the successful party against the expense to which that party has been put by reason of the legal proceedings.[35]
  4.         The usual rule as to costs is that costs are to follow the event, such that the successful party to an action or proceeding is entitled to recover their costs.  This emerges from O 66 r 1(1) of the Rules of the Supreme Court 1971 (WA) (RSC).  This is because ordinarily it is just that the party who turns out to have unjustifiably brought the other party before the court should be required to pay the other party’s costs.[36] 
  5.         Of course, where it is appropriate, there can be departures from this rule.  
  6.         The conduct of the plaintiff was characterised by the defendant as representing an unnecessary escalation of the dispute, with the defendant considering the matter should have been mediated, rather than having the arbitral pathway invoked.  
  7.         However, as I explained at the hearing, cl 18 is expressed disjunctively and allows a party (whether the owner or the builder) to pursue arbitration without first exhausting the mediation process.
  8.         Further, the plaintiff’s conduct to date has involved nothing more than an adherence to the parties’ bargain.  The plaintiff, and his solicitors, initiated the dispute process through the formal Notice of Dispute, have sought to have an arbitrator appointed by consent, and in the face of a refusal by the defendant to agree an arbitrator, the solicitors have then invoked the regime to have an arbitrator appointed.  Ordinarily, that mechanism would have resulted in the appointment of an arbitrator and the process would have continued.  The HIA’s refusal has provided something of a ‘fly in the ointment’ here, but in the face of that refusal, the plaintiff again sought the defendant’s consent to an arbitrator, and made plain his intention to bring an application to this court under s 11(4), with possible adverse costs consequences.
  9.         The correspondence from the plaintiff’s solicitors has been clear and direct, and should have left the defendant in little doubt that she risked the possibility of an adverse costs order if the plaintiff was put to the expense of this application.
  10.         In my view, the defendant was unable to point to any matters which would justify a departure from the usual rule, whether to preclude an award of costs in the plaintiff’s favour or to reduce the costs which might otherwise be awarded to the plaintiff.   On my assessment, the application to this court was necessary and appropriate in order to overcome the stalemate in the arbitral process caused by the appointing authority’s refusal.[37]
  11.         For these reasons, the appropriate exercise of the court’s discretion was to make an award of costs in the plaintiff’s favour, on a party/party basis.   

Conclusion and orders

  1.         For the foregoing reasons, I made the following orders on the plaintiff’s application:

1.         Pursuant to s 11(4)(c) of the Commercial Arbitration Act 2012 (WA), Mr Scott Ellis is hereby appointed as the arbitrator in respect of the dispute articulated in the Notice of Dispute attached as ‘JNM-16’ to the affidavit of Jonathan Neil Miller affirmed on 15 September 2026, for the purposes of the ‘Building Contract’ which is attached as ‘JNM-3’ to that same affidavit.

2.         The defendant is to pay the plaintiff’s costs of and incidental to the application of the plaintiff by originating summons dated 18 September 2026, to be assessed if not agreed and payable forthwith.

  1.         Finally, I repeat the sentiments I expressed to both parties at the conclusion of the hearing on 9 October 2026, to the effect that the parties should do their best to find some way to resolve this dispute before the arbitral proceedings became further protracted, given the likelihood that the legal costs of that process may well start to outpace the quantum of the dispute.  

I certify that the preceding paragraph(s) comprise the reasons for decision of the Supreme Court of Western Australia.

AB

Associate to the Hon Justice Lundberg

12 OCTOBER 2026

[1] Described as the ‘West Australian Lump Sum Building Contract for New Builds, Alterations and Additions dated 20 April 2024’: Miller Affidavit, Annexure JNM-3.

[2] I note there is a typographical error in cl 18(a) and a historical reference to the Commercial Arbitration Act 1985 (WA) in cl 18(b), but neither of these are of legal consequence in the present matter.

[3] PS [8] and [9].  The invoice is Invoice No. 2361.

[4] PS [10].

[5] For example, VO2, VO6, VO7, VO9 and VO10: Miller Affidavit, Attachment JNM-4

[6] Miller Affidavit [45].

[7] Miller Affidavit, JNM-16.

[8] Miller Affidavit, Attachment JNM-17.

[9] Miller Affidavit, Attachment JNM-18.

[10] Miller Affidavit, Attachment JNM-19

[11] Miller Affidavit, Attachment JNM-20.

[12] Miller Affidavit, Attachments JNM-21 and JNM-22.

[13] Miller Affidavit, Attachment JNM-23.

[14] Building Services Regulations, reg 6(2).

[15] Miller Affidavit, Attachment JNM-24.

[16] Henderson & Anor v Aintree Holdings Pty Ltd [2021] WASAT 113.

[17] Shakur v Aintree Holdings Pty Ltd [2015] WASAT 12.

[18] Monaghan Affidavit, [4].

[19] John Hockley, Clyde Croft, William KQ Ho and Kieran Hickie, Australian Commercial Arbitration (3rd edition, 2026), [11.30].

[20] Gemcan Constructions Pty Ltd v Westbourne Grammer School [2020] VSC 429 [46] (Lyons J).

[21] Gemcan Constructions Pty Ltd v Westbourne Grammer School [53].

[22] Tulip Bay Pty Ltd v Structural Monitoring Systems Ltd [2019] WASC 223 (Kenneth Martin J).

[23] EEPL Holdings v Clifford Chance [2026] WASC 368 [73] – [78] (Lundberg J).

[24] Pipeline Services WA Pty Ltd v ATCO Gas Australia Pty Ltd [2014] WASC 10 [44] (Martin CJ) and the authorities therein cited.

[25] Fitzpatrick v Emerald Grain Pty Ltd [2017] WASC 206 [49] (Martin CJ).

[26] IBM Australia Ltd v National Distribution Services Ltd (1991) 22 NSWLR 466, 475 and 477 (Kirby P), 483 (Clarke JA), and 487 (Handley JA).

[27] IBM Australia Ltd v National Distribution Services Ltd (483) (Clarke JA).

[28] Pipeline Services WA Pty Ltd v ATCO Gas Australia Pty Ltd [2014] WASC 10 [44] (Martin CJ) and the authorities therein cited.

[29] PS [25] – [26].

[30] PS [27] – [28].

[31] Tulip Bay Pty Ltd v Structural Monitoring Systems Ltd [19] (Kenneth Martin J).

[32] Gemcan Constructions Pty Ltd v Westbourne Grammer School [63] – [76] (Lyons J).

[33] Applying the generally accepted meaning of that phrase as appears in Maritime Services Board (NSW) v Liquor Administration Board (1990) 21 NSWLR 180, 196 (Campbell J).

[34] Frigger v Lean [2012] WASCA 66 [53].

[35] Latoudis v Casey (1990) 170 CLR 534.

[36] Smolarek v Roper [2009] WASCA 124 (S) [3] (Wheeler and Pullin JJA, Newnes AJA).

[37] See, example, the approach as to costs adopted by this court in the context of an application under s 11(3) of the CAA in Browne’s Limestone Constructions Pty Ltd v Georgiou Group Pty Ltd [2021] WASC 181 (Kenneth Martin J).

End

Arbwatch Newsletter

Doyles Arbitration Lawyers provides the Arbwatch, a regular newsletter, highlighting new and important developments and cases in Arbitration law. 

The subject matter focusses on the Australian jurisdiction, however we also regularly highlight international arbitral cases of import or interest.  

We respect your privacy. Sign up below, it’s free and you can unsubscribe at any time: